A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leave off The total number of days to complete the work is? - Study24x7
Social learning Network
study24x7

Default error msg

Login

New to Study24x7 ? Join Now
Already have an account? Login
15 Mar 2019 09:59 AM study24x7 study24x7

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leave off The total number of days to complete the work is?

A

6 3/5

B

8 1/2

C

10 1/5

D

13 1/2

study24x7
Write a comment
Related Questions
500+   more Questions to answer
Most Related Articles