A can do a piece of work in 12 days. When he had worked for 2 days B joins him. If the complete work was finished in 8 days. In how many days B alone can finish the work? - Study24x7
Social learning Network
study24x7

Default error msg

Login

New to Study24x7 ? Join Now
Already have an account? Login
27 followers study24x7 02 Jul 2021 11:24 AM study24x7 study24x7

A can do a piece of work in 12 days. When he had worked for 2 days B joins him. If the complete work was finished in 8 days. In how many days B alone can finish the work?

A

18 days

B

12 days

C

24 days

D

10 days

study24x7
Write a comment
Related Questions
500+   more Questions to answer
Most Related Articles