When slack of an activity is negative

A

it represents a situation where extra resources are available and the completion of project is not delayed

B

it represents that a programme falls behind schedule and additional resources are required to complete the project in time

C

the activity is critical and any delay in its performance will delay the completion of whole project

D

all of the above